Who Gets the Power? Singapore's Data Centre Capacity Rules, Explained for AI Buyers
In most countries, a company that wants to build a data centre buys land, applies for a power connection and starts digging. In Singapore it applies to the government and waits to hear whether it has been chosen.
That difference shapes everything about hosting AI hardware here: what it costs, what kind of building it goes into, and why your colocation provider talks so much about sustainability. If you buy AI infrastructure in Singapore, this policy is part of your purchase, whether or not it appears on the quote.
The story in six steps
| When | What happened |
|---|---|
| ⏸️ Before 2022 | A moratorium on new data centre construction |
| 🚪 2022 | The moratorium is lifted and a pilot "Data Centre – Call for Application" begins |
| 🏁 2023 | The pilot allocates 80 MW to four operators |
| 🗺️ May 2024 | IMDA publishes the Green Data Centre Roadmap: at least 300 MW more in the near term, with potentially 200 MW or more on top through green energy |
| 📣 1 December 2025 | EDB and IMDA launch the second call, DC-CFA2, offering at least 200 MW |
| ✅ 21 August 2026 | Results announced: four operators, each with a provisional 50 MW |
Sources: Reed Smith on Singapore's data centre expansion, Data Center Dynamics on the Green Data Centre Roadmap, Withers on DC-CFA2, W.Media on the DC-CFA2 results, eWeek. Bars show megawatts relative to the roadmap's 300 MW.
How scarce is it?
The Economic Development Board's figures, as reported by eWeek, are that Singapore hosts more than 70 data centres with roughly 1.4 GW of capacity. The 200 MW from the latest round is about 14% of that. The allocation is provisional, so it represents future capacity for those operators and not buildings that are already running.
For scale: one GB300 NVL72 rack draws on the order of 130 to 140 kW. We will leave the arithmetic to the reader, with the caution that a data centre's megawatts also cover cooling and everything else, so the number of racks is lower than simple division suggests.
What it takes to be chosen
The second call set a higher bar than the pilot. Legal commentary on DC-CFA2 highlights two requirements in particular.
| Requirement | What it means |
|---|---|
| 🌱 Green energy | At least 50% of the facility's power from eligible green pathways |
| 🏅 Building standard | BCA-IMDA Green Mark for Data Centres 2024 Platinum certification, mandatory |
The operators selected went further. According to reporting on the announcement, they committed to exceed the minimum sustainability requirements and to adopt technologies including liquid cooling.
Source: Conventus Law on DC-CFA2. This is a summary of published commentary, not legal advice. Refer to IMDA and EDB for the authoritative requirements.
What this means if you are buying AI hardware
1. Space in Singapore carries a premium, and that is by design
Capacity is rationed, and the ration goes to operators who meet demanding standards. That costs money to build, and it is reflected in what tenants pay. It is the main reason the comparison in Singapore or Johor: Where to Host an AI Rack exists at all.
2. New capacity is built for liquid cooling
With the newest allocations committing to liquid cooling, the halls coming online over the next few years will suit rack-scale AI systems better than most of what exists today. If your timeline allows, ask providers what is coming, not only what is available. Singapore's standard for these systems is covered in SS 726:2026 Explained.
3. Your provider's sustainability questions are not small talk
An operator held to efficiency and green-energy commitments has a direct interest in what tenants install. Expect questions about power density, cooling type and efficiency. Efficient hardware is easier to place.
4. Existing halls still matter most
The new megawatts take years to arrive. For a deployment in the next twelve months you are almost certainly choosing among buildings that already exist, many of them designed for air cooling. That is the practical context for Can Your Singapore Colocation Hall Take a 140 kW Rack?
The debate
The criticism: rationing capacity while AI demand surges pushes investment to neighbouring countries. Johor's growth as a data centre location is partly a consequence. Some in the industry argue that Singapore is trading away scale.
The reply: Singapore has little land and limited access to renewable energy, and data centres are heavy users of both power and water. Allocating capacity selectively, to the most efficient and highest-value projects, is a deliberate choice to stay a hub without letting one industry absorb the grid. The roadmap also leaves the door open: capacity beyond the base figure is available to operators who bring their own green energy.
Both views are reasonable, and the policy is still moving. Reporting on the August 2026 results noted that a third call for applications is possible.
Four questions to ask a Singapore colocation provider
- How much power can you commit to us, and at what rack density?
- Is the hall liquid-cooling ready today, or planned?
- What share of the facility's power comes from green sources, and how is that documented?
- What new capacity do you have coming, and when?